Sample Report · Project Management

Project Status Report — Sample

A completed status report for a project in trouble — what honest reporting looks like when the news is bad, the three numbers that carry it, and the decision it asks for.

Markdown. No sign-up, no email.

This is an illustrative example. The project and figures are composed to show what honest reporting looks like when the news is bad, not drawn from a named engagement.

Project: Customer portal replacement Period: Month 8 of 12 Prepared by: Delivery manager For: Sponsor

1. The headline#

Would I personally bet on the current end date? No.

By how much: 6–9 weeks, on current scope.

Since when did I know: the trend has been visible for around six weeks. I am reporting it now having confirmed it against the numbers below rather than raising it as a feeling.

2. Progress#

Timeline elapsed70%
Budget consumed68%
Scope completed and accepted41%

The first two numbers have been reported for eight months and are reassuring. The third has not been tracked until this period, and it is the one that predicts the end date.

Claimed "90% done" for more than two weeks: 3 items (payments integration, notification service, admin permissions).

3. What changed#

PeriodChanges approvedSchedule impact
Months 1–34+2 weeks
Months 4–67+5 weeks
Months 7–83+2 weeks
Cumulative14+9 weeks

Cost impact cumulative: +£142,000. Scope removed to absorb any of it: none.

Each change was assessed and approved individually and each was reasonable. This is the first time they have been added up.

4. Blocked#

WhatBlocked sinceWaiting onEscalate?
Payments integration61 daysThird-party API contractyes — needs you
SSO configuration22 daysInternal security reviewyes
Address lookup licence17 daysProcurementyes
3 further items14–19 daysVariousmonitoring

Average time to obtain a decision this period: 9 days.

The team works in two-week iterations. A nine-day decision means most iterations contain a stall, and the team has adapted by working around blockers rather than escalating them — which is why this has not surfaced in previous reports.

5. Quality#

Open defects34 (4 high, 18 medium, 12 low)
Trendrising
Untested areaspayments, notifications, reporting
Integration attemptedno
Non-functional testingnot started

Integration with the two upstream systems has not been attempted. Testing is scheduled to begin in month 10. Both are deferred risk rather than absent risk.

6. Decision needed this week#

#DecisionWhoByCost of not deciding
1Reduce scope, or move the dateSponsor15thBoth happen anyway, later and without a choice
2Escalate the payments API contractSponsor12thAdds ~1 week per week of delay
3Delegate approvals below £10kSponsor15th9-day decision latency continues

Options for decision 1, with what each costs:

  • Hold the date, reduce scope. Defer reporting module and 4 of the 14 approved changes. Recovers ~5 weeks. Recommended.
  • Hold scope, move the date. New date: mid-March. No further cost beyond the extension.
  • Hold both. Requires 3 additional engineers by the 20th; onboarding cost means the net recovery is roughly 2 weeks, not 6.

7. Next period#

CommitmentConfidence
Payments integration complete (if contract lands by 12th)low
Notification service acceptedmedium
Begin integration testinghigh

Why this report reads the way it does. The project has been green for four months on effort metrics while accepted scope fell behind. Nothing was concealed; the numbers that would have shown it were not being reported.

Three figures carry the whole report — 41% against 70%, +9 weeks of un-totalled change, and 9-day decision latency. Each was available months ago. The report now includes them by default so this cannot recur quietly.

See project management, the health check, the status report template, and the worked example of the review that produced these numbers.