Template · Project Management

Status Report Template That Does Not Hide Trouble

A one-page status report built so a slipping project cannot look green, confidence in the date rather than a colour, what changed, what is blocked and for how long, and the decision needed this week.

About the numbers here. Numbers in a template are placeholders to replace with your own, not measurements.

Markdown. No sign-up, no email.

Most status reports are green until they are red. This one is structured so that the things which predict lateness (ageing blockers, decision latency, cumulative change) appear whether or not anyone volunteers them.

One page. If it takes half a day to produce, it is consuming the capacity that should be removing blockers.

Project: _______________ Reporting period: _______ Prepared by: _______________ For: _______________

1. The headline#

Would I personally bet on the current end date? yes / no / not any more

If no: by how much, and since when did I know? _______________

This replaces a status colour deliberately. "Amber" is a word that lets everyone defer the conversation; a direct answer to a direct question does not. Projects rarely fail through one event: they fail through a series of "we will catch up next sprint" judgements, none of which is ever escalated.

2. Progress#

This period
Completed and accepted
In progress
Not started, planned for next period

Measured by accepted work, not effort spent. Effort spent is a measure of activity; accepted work is a measure of progress, and only one of them predicts a delivery date.

Anything claimed "90% done" for more than two weeks: _______________

3. What changed#

ChangeImpact on dateImpact on costApproved by

Cumulative since baseline: schedule ____, cost ____

The cumulative row is the one that matters and the one nobody volunteers. Fifteen individually reasonable changes have added eleven weeks; each was assessed alone.

4. Blocked#

WhatBlocked sinceWaiting onChasedEscalate?

Oldest blocker: ____ days. Average time to get a decision this period: ____

Delay lives in queues rather than in the work. If the team waits a week for decisions, no delivery improvement changes the outcome, and this table is where that becomes visible to the person who can fix it.

5. Risks that moved#

Only the ones that changed. A full register read-out belongs in the risk register, not here.

RiskWasNowWhyAction

Overdue mitigations: ____

6. Quality signals#

Open defects, by severity
Trend, rising or falling as we approach the end
Anything substantial still untested
Non-functional requirements tested?yes / no

Defects rising as the end approaches, or a large untested area, are the two most reliable predictors of a late finish. They belong in the report before they are a crisis.

7. Decision needed this week#

#DecisionWho decidesBy whenCost of not deciding
1

The last column converts a request into a consequence, which is what turns an unread item into a decision.

If there is nothing here, say so explicitly. A report that never asks for anything trains the sponsor to skim it.

8. Next period#

CommitmentOwnerConfidence
high / medium / low

Written for people who will read one page. Anything requiring more detail goes in an appendix nobody is obliged to open, and if the appendix is where the real news is, this report has failed at its only job.

Back to Project Management

Get new material when it is published

Everything here is free and stays free. There is no form in front of any document. If you want to know when new guides and templates go up, leave an email.

Roughly monthly. Unsubscribe in one click. We do not share your address, and we will not call you.