Template · Project Management

Status Report Template That Does Not Hide Trouble

A one-page status report built so a slipping project cannot look green — confidence in the date rather than a colour, what changed, what is blocked and for how long, and the decision needed this week.

Markdown. No sign-up, no email.

Most status reports are green until they are red. This one is structured so that the things which predict lateness — ageing blockers, decision latency, cumulative change — appear whether or not anyone volunteers them.

One page. If it takes half a day to produce, it is consuming the capacity that should be removing blockers.

Project: _______________ Reporting period: _______ Prepared by: _______________ For: _______________

1. The headline#

Would I personally bet on the current end date? yes / no / not any more

If no — by how much, and since when did I know? _______________

🔴 This replaces a status colour deliberately. "Amber" is a word that lets everyone defer the conversation; a direct answer to a direct question does not. Projects rarely fail through one event — they fail through a series of "we will catch up next sprint" judgements, none of which is ever escalated.

2. Progress#

This period
Completed and accepted
In progress
Not started, planned for next period

Measured by accepted work, not effort spent. Effort spent is a measure of activity; accepted work is a measure of progress, and only one of them predicts a delivery date.

Anything claimed "90% done" for more than two weeks: _______________

3. What changed#

ChangeImpact on dateImpact on costApproved by

Cumulative since baseline: schedule ____ · cost ____

The cumulative row is the one that matters and the one nobody volunteers. Fifteen individually reasonable changes have added eleven weeks; each was assessed alone.

4. Blocked#

WhatBlocked sinceWaiting onChasedEscalate?

Oldest blocker: ____ days. Average time to get a decision this period: ____

Delay lives in queues rather than in the work. If the team waits a week for decisions, no delivery improvement changes the outcome — and this table is where that becomes visible to the person who can fix it.

5. Risks that moved#

Only the ones that changed. A full register read-out belongs in the risk register, not here.

RiskWasNowWhyAction

Overdue mitigations: ____

6. Quality signals#

Open defects, by severity
Trend — rising or falling as we approach the end
Anything substantial still untested
Non-functional requirements tested?yes / no

Defects rising as the end approaches, or a large untested area, are the two most reliable predictors of a late finish. They belong in the report before they are a crisis.

7. Decision needed this week#

#DecisionWho decidesBy whenCost of not deciding
1

The last column converts a request into a consequence, which is what turns an unread item into a decision.

If there is nothing here, say so explicitly — a report that never asks for anything trains the sponsor to skim it.

8. Next period#

CommitmentOwnerConfidence
high / medium / low

Written for people who will read one page. Anything requiring more detail goes in an appendix nobody is obliged to open — and if the appendix is where the real news is, this report has failed at its only job.